Home Electric Service New Account New Construction
New Construction PDF Print E-mail
Member is responsible for providing a cleared right-of-way.

Overhead Line Extension
Single-Phase:  4.25 per foot   *Plus $1300.00 construction fee
Three-Phase:   $11.50 per foot
30ft Meter Pole: $200 plus tax.

Underground Line Extension 
Member is responsible to provide 4ft deep trench.
Single-Phase: 8.50 per foot
Three-Phase:  $15.00 per foot
Padmount Transformer Charge
Single-Phase: $600
Three-Phase: $3,000 
*No underground will be installed between December 1st to April 1st

Overhead to underground conversion fee:
Single-Phase: $800
Three-Phase: $2,400

$300 plus tax for a pole pedestal. 
$425 plus tax for a 200A free standing meter pedestal.
$775 plus tax for a 400A free standing meter pedestal.
Member is responsible for installing, maintaining and locating secondary conductor from pedestal to house.

Trenching: $200.00 plus $1.50 per foot (where feasible)

Plowing: $400.00 plus $ .50 per foot  (where feasible)

Credit
All contribution in aid of construction, other than underground conversion and transformer charges, are refundable at a 3.7¢ per kilowatt hour credit on your monthly bill once the service is connected.  This will continue for three years or until contribution is fully refunded, whichever comes first.
Prices subject to change without notice.

Last Updated on Monday, 25 July 2011 09:36
 

"Our Energy Working for You"

 
AddThis Social Bookmark Button
wattsmodule
WattsSmartmodule
UseWisely
LivingEnergyIowa

Member Poll

How Have You Learned About Touchstone Energy?